- Round table discussion was held to identify the owner's objectives and future vision for the woodland.
- An action plan timetable was created to track progress and schedule key activities.
- A request for inspection of larch has been submitted to Natural Resources Wales (NRW).
- The felling licence application has been submitted, including details of restocking plans.
- Woodland management plan drafted and submitted to NRW for approval.
- Meeting held with the chosen contractor to discuss the programme of works and extraction route.
- Ongoing liaison between NRW and the plan’s author to ensure target approval date of 1st September 2024.
Next Steps?
- Await NRW approval for the woodland management plan.
- Finalise details with the chosen contractor and commence work according to the agreed schedule.
- Monitor and evaluate the progress of the project against the action plan timetable.
- Continue to work with NRW to address any emerging issues or concerns.