Glyn Arthur Project Update - July 2024

  • Round table discussion was held to identify the owner's objectives and future vision for the woodland.

  • An action plan timetable was created to track progress and schedule key activities.

  • A request for inspection of larch has been submitted to Natural Resources Wales (NRW).

  • The felling licence application has been submitted, including details of restocking plans.

  • Woodland management plan drafted and submitted to NRW for approval.

  • Meeting held with the chosen contractor to discuss the programme of works and extraction route.

  • Ongoing liaison between NRW and the plan’s author to ensure target approval date of 1st September 2024.

Next Steps?

  • Await NRW approval for the woodland management plan.

  • Finalise details with the chosen contractor and commence work according to the agreed schedule.

  • Monitor and evaluate the progress of the project against the action plan timetable.

  • Continue to work with NRW to address any emerging issues or concerns.