Glyn Arthur Project Update - July 2024
Round table discussion was held to identify the owner's objectives and future vision for the woodland.
An action plan timetable was created to track progress and schedule key activities.
A request for inspection of larch has been submitted to Natural Resources Wales (NRW).
The felling licence application has been submitted, including details of restocking plans.
Woodland management plan drafted and submitted to NRW for approval.
Meeting held with the chosen contractor to discuss the programme of works and extraction route.
Ongoing liaison between NRW and the plan’s author to ensure target approval date of 1st September 2024.
Next Steps?
Await NRW approval for the woodland management plan.
Finalise details with the chosen contractor and commence work according to the agreed schedule.
Monitor and evaluate the progress of the project against the action plan timetable.
Continue to work with NRW to address any emerging issues or concerns.